Published on Fri., June 6, 2014

New HHS Baseball and Softball Field RenderingThe track at Heritage High School will be closed starting June 9 for construction of the new high school. This will include the track, football, baseball, and softball fields. These will remain closed until the new facilities open.

The following activities will be taking place during the months of June, July, and August 2014 at Heritage High School:

Phase I (New baseball & softball fields adjacent to Wards Ferry Road)

  • Grading
  • Site Utilities
  • Retaining Walls

Phase II (New school corner of Timberlake & Wards Ferry Road)

  • Site Demolition
  • Grading
  • Site Utilities
  • Concrete Footings

 